The overweight oversize shipment of the MV Alanis docked at Construction Jetty port of Long Son construction site on December 23rd has been received, cleared and transported to the construction site of the Petrochemical Complex in the Soutgh of Vietnam Project on December 26, 2020 by Vietranstimex.
The MV Alanis released more than 1,700 tons of cargoes including particular overweight oversize equipment such as Main washer weighing more than 160.9 tons, dimensions of 68.04m x 5.13m x 5.73m; Butadiene Tower weighting 76 tons, dimension of 42.71mx 3.29m x 3.66 m; Predistill Ation Tower weighting 67.03 tons, dimensions of 43.09m x 3.27m x 3.82 m; Depentanizer weighting more than 81 tons, dimensions of 42.71m x 3.29m x 3.66 m, …
In order to receive and transport these equipment, convoys of SPT hydraulic trailers of 7-axle, 10-axle have been mobilized, particularly for large items of 40m or more, SPMT self-propelled hydraulic trailers up to 24 axles have been used